Franklin City Hall Masterplan

13 Establishing The Vision Franklin City Hall Master Plan City Hall Opens 2026 04Construction Documents PHASE PHASE 04.A Executive Team Kick-Off PHASE 04.B 50% Construction Documents Update Construction Cost Estimate PHASE 04.C 100% Contract Documents 06Construction Administration & Project Close Out PHASE PHASE 06.A Construction Begins PHASE 06.B Project Close-Out LEED Commissioning PHASE 05.A Bidding & Negotation LEED Design Compliance Review by USGBC PHASE 05.B BOMA Worksession MILESTONE 04: BOMA Meeting Resolution to Approve Bid Award PHASE 06.C City Issues Use & Occupancy Certificate Move-In PHASE 05.C Permit Approval Contractor Notice to Proceed Permitting, LEED Design Compliance Review, and Bidding & Negotiation 05 PHASE